Backstage Construction Schedule – August 9 – 15
August 13, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for August 9 – 15, 2014. Updated August 13.
Please click here for general information on concrete pours.
Saturday, August 9
- 12th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 9:30 am.
- Concrete Finishing until to 10:00 pm.
Monday, August 11
- A 12th and 13th floor wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 1:00 pm.
Tuesday, August 12
- Rebar delivery from 7:00 am.
- 13th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Wednesday, August 13
- 13th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Thursday, August 14 – UPDATED
- A 13th floor wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 1:00 pm.
- Toro Aluminum will be delivering a tractor trailer load of windows at 3:00 pm. The tractor trailer will be occupying the south curb lane of The Esplanade during unloading.
- Eastbound traffic from Yonge Street will be impacted temporarily. Pedestrians will be able to have access through the site during unloading. We apologize any inconvenience this may cause.
Friday, August 15
- Rebar delivery from 7:00 am.
- 13th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-August-9-15-2014