Backstage Construction Schedule – August 2 – 9
August 7, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for August 2 – 8, 2014.
Please click here for general information on concrete pours.
Saturday, August 2
- A 5-man crew form Italform removing forming from the west side of the building, from 9:00 am.
- A 2-man crew from Dominus removing the concrete curd on the 5th floor, from 9:00 am.
Monday, August 4 – Site Closed – Civic Holiday
Tuesday, August 5
- A 11th and 12th floor wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Wednesday, August 6
- 12th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Thursday, August 7
- Rebar delivery from 7:00 am.
- 11th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Friday, August 8
- Rebar delivery from 7:00 am.
- A 12th and 13th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Saturday, August 9 – updated
- 12th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 9:30 am.
- Concrete Finishing until to 10:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-August-2-9-2014