Backstage Construction Schedule – July 12 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 12 – July 18, 2014.

Backstage construction site Friday July 11 2014

Backstage construction site Friday July 11 2014

Please click here for general information on concrete pours.

Saturday, July 12

  • A forming crew working on 8th floor wall and 9th floor slab
  • Dominus crew doing construction housekeeping on-site.

Monday, July 14

  • An 8th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

 Tuesday, July 15

  • Rebar delivery from 7:00 am.
  • 9th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, July 16

  • An 8th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

Thursday, July 17

  • 9th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 Friday July 18

  • Rebar delivery from 7:00 am.
  • 9th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

L Tower Construction Schedule July 12 – 18

This is the current construction schedule for 8 The Esplanade – L Tower  – July 12 – July 18, 2014

The L Tower, crane and hoist, Friday, July 11 2014

The L Tower, crane and hoist, Friday, July 11 2014

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Saturday, July 12

  • Some interior work on site.

Monday, July 14

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, July 15

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, July 16

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, July 17

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, July 18

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Hoist Issues at L Tower today — Apologies for Traffic Delays

Unfortunately there were some issues today with deliveries for both LTower and Backstage due to problems with the hoist (external elevator).

This caused some traffic delays in the area.

We pass on the Construction Management Teams apologies for the inconvenience.

Backstage Construction Schedule – July 5 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 5 – July 11, 2014.

Backstage Condominium at Yonge Street and The Esplanade, July 4, 2014

Backstage Condominium at Yonge Street and The Esplanade, July 4, 2014

Please click here for general information on concrete pours.

Saturday, July 5

  • Miscellaneous construction work is scheduled on site from 9:00 am.

Monday, July 7

  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

 Tuesday, July 8

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

Wednesday, July 9

  • Final Eighth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
  • Concrete Finishing may be required until to 10:00 pm.

Thursday, July 10

  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

 Friday July 11

  • Rebar delivery from 7:00 am.
  • First Ninth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
  • Concrete Finishing may be required until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

L Tower Construction Schedule July 5 – 11

This is the current construction schedule for 8 The Esplanade – L Tower  – July 5 – July 11, 2014

 

The L Tower as seen from St. Lawrence Market (North), Friday July 4, 2014

The L Tower as seen from St. Lawrence Market (North), Friday July 4, 2014

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Saturday, July 5

  • Some interior work on site.

Monday, July 7

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, July 8

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, July 9

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, July 10

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, July 11

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.