Backstage reaches 10th storey — Construction Schedule – July 26 – August 1

Backstage has reached it’s 10th floor wall and concrete pouring will commence for the  11th floor slab on July 29. 

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 26 – August 1, 2014.

 

Backstage condominium: concrete truck pouring concrete.

Backstage condominium: concrete truck unloading.

Please click here for general information on concrete pours.

Saturday, July 26

  • A forming crew working on 10th floor wall and 11th floor slab from 9:00 am. 
  • Dominus crew doing construction housekeeping on-site.

Monday, July 28

  • A  10th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

 Tuesday, July 29

  • Rebar delivery from 7:00 am.
  •  11th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, July 30

  • 11th  Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, July 31

  • A 11th  floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

 Friday, August 1

  • Rebar delivery from 7:00 am.
  • 11th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 10th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: