Backstage reaches 10th storey — Construction Schedule – July 26 – August 1
July 25, 2014 Leave a comment
Backstage has reached it’s 10th floor wall and concrete pouring will commence for the 11th floor slab on July 29.
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for July 26 – August 1, 2014.
Please click here for general information on concrete pours.
Saturday, July 26
- A forming crew working on 10th floor wall and 11th floor slab from 9:00 am.
- Dominus crew doing construction housekeeping on-site.
Monday, July 28
- A 10th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Tuesday, July 29
- Rebar delivery from 7:00 am.
- 11th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Wednesday, July 30
- 11th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Thursday, July 31
- A 11th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.
Friday, August 1
- Rebar delivery from 7:00 am.
- 11th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour for 10th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-July-26-August-1-2014