Backstage Construction Schedule – July 19 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 19 – July 25, 2014.

Concrete pour today at the Backstage Condo, July 18, 2014.

Concrete pour today at the Backstage Condo, July 18, 2014.

Please click here for general information on concrete pours.

Saturday, July 19

  • A forming crew working on 8th floor wall and 9th floor slab from 9:00 am. 
  • Dominus crew doing construction housekeeping on-site.

Monday, July 21

  • A 9th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

 Tuesday, July 22

  • Rebar delivery from 7:00 am.
  • 10th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, July 23

  • 10th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, July 24

  • A 10th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

 Friday July 25

  • Rebar delivery from 7:00 am.
  • 10th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 10th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: