Backstage Construction Schedule – July 12 – 18
July 11, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for July 12 – July 18, 2014.
Please click here for general information on concrete pours.
Saturday, July 12
- A forming crew working on 8th floor wall and 9th floor slab
- Dominus crew doing construction housekeeping on-site.
Monday, July 14
- An 8th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.
Tuesday, July 15
- Rebar delivery from 7:00 am.
- 9th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Wednesday, July 16
- An 8th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.
Thursday, July 17
- 9th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
Friday July 18
- Rebar delivery from 7:00 am.
- 9th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
- An after-slab concrete pour to begin following the main slab pour.
- Concrete Finishing until to 10:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-July-12-18-2014