Backstage Construction Schedule – July 5 – 11
July 4, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for July 5 – July 11, 2014.
Please click here for general information on concrete pours.
Saturday, July 5
- Miscellaneous construction work is scheduled on site from 9:00 am.
Monday, July 7
- A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.
Tuesday, July 8
- Rebar delivery from 7:00 am.
- A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.
Wednesday, July 9
- Final Eighth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
- Concrete Finishing may be required until to 10:00 pm.
Thursday, July 10
- A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.
Friday July 11
- Rebar delivery from 7:00 am.
- First Ninth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
- Concrete Finishing may be required until to 10:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-July-5-11-2014