Backstage Construction Schedule – July 5 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 5 – July 11, 2014.

Backstage Condominium at Yonge Street and The Esplanade, July 4, 2014

Backstage Condominium at Yonge Street and The Esplanade, July 4, 2014

Please click here for general information on concrete pours.

Saturday, July 5

  • Miscellaneous construction work is scheduled on site from 9:00 am.

Monday, July 7

  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

 Tuesday, July 8

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

Wednesday, July 9

  • Final Eighth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
  • Concrete Finishing may be required until to 10:00 pm.

Thursday, July 10

  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

 Friday July 11

  • Rebar delivery from 7:00 am.
  • First Ninth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
  • Concrete Finishing may be required until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: