Backstage Construction Schedule – June 28 – July 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 28 – July 4, 2014.

The Backstage condo begins its rise above the podium.

The Backstage condo begins its rise above the podium.

Please click here for general information on concrete pours.

Saturday, June 28

  • No work is scheduled on site.

Monday, June 30

  • No work is scheduled on site.

 Tuesday, July 1 – Canada Day

  • Site Closed for the Holiday.

Wednesday, July 2

  • Final seventh floor concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 7:00 pm.
  • Concrete Finishing may be required until to 11:00 pm.

Thursday, July 3

  • First Eighth floor concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 7:00 pm.
  • Concrete Finishing may be required until to 11:00 pm.

 Friday July 4

  • Second Eighth floor concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 7:00 pm.
  • Concrete Finishing may be required until to 11:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: