Backstage Construction Schedule – June 21 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 21 – 27, 2014.

Backstage condo under construction, June 20, 2014

Backstage condo under construction, June 20, 2014

Please click here for general information on concrete pours.

Saturday, June 21

  • Seventh floor slab concrete pour #2 by subcontractor Italform, scheduled to begin at 9:00 am.
  • Concrete Finishing to 7:00 pm.

Monday, June 23

  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Tuesday, June 24

  • Rebar (steel) delivery starting at 7:00 am
  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

Wednesday, June 25

  • Seventh floor slab concrete pour #3 by subcontractor Italform, scheduled to begin at 10:00 am.
  • Concrete Finishing to 9:00 pm.

Thursday, June 26

  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

 Friday June 27

  • Rebar (steel) delivery starting at 7:00 am
  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: