Backstage Construction Schedule – June 14 – 20
June 13, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for June 14 – 20, 2014.
Please click here for general information on concrete pours.
Saturday, June 14
- No work is scheduled.
Monday, June 16
- Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.
Tuesday, June 17
- Rebar (steel) delivery starting at 7:00 am
- Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.
Wednesday, June 18
- Seventh floor slab concrete pour #1 by subcontractor Italform, scheduled to begin at 10:00 am.
- Concrete Finishing to 7:00 pm.
Thursday, June 19
- Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.
Friday June 20
- Rebar (steel) delivery starting at 7:00 am
- Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-June-14-20-2014