Backstage Construction Schedule – May 24 – 30
May 23, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for May 24 – 30, 2014.
Please click here for general information on concrete pours.
Saturday, May 24
- Excavation work on site from 9:00 am to Noon
- Some general interior work
Monday, May 26
- Rebar (steel) delivery starting at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.
Tuesday, May 27
- Fifth floor slab concrete pour #8 by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Wednesday, May 28
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.
Thursday, May 29
- Rebar (steel) delivery starting at 7:00 am.
- Fifth floor slab concrete pour #9 by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Friday, May 30
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-May-24-30-2014