Backstage Construction Schedule – May 17 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 17 – 23, 2014.

Backstage Condo - podium concrete detail.

Backstage Condo – podium concrete detail.

Please click here for general information on concrete pours.

 

Saturday, May 17

 

  • Excavation work on site from 9:00 am to Noon 
  • Some general interior work

Monday, May 19 – Victoria Day Holiday

  • Site Closed for the holiday.

 Tuesday, May 20

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Wednesday, May 21

  • Fifth floor slab concrete pour #7 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Thursday, May 22

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Friday, May 23

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: