Backstage Construction Update – May 8 – 9
May 7, 2014 Leave a comment
This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium – for May 8 – 9, 2014.
Please click here for general information on concrete pours.
Thursday, May 8 – UPDATE
- Fifth floor slab concrete pour #3 by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Friday, May 9
- Rebar (steel) delivery starting at 7:00 am.
- Possible Wall & Column concrete pour from 1:00 pm to 6:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.