Backstage Construction Schedule – May 31 – June 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 31 – June 6, 2014.

Please click here for general information on concrete pours.

First floor of the Backstage condo's tower section.

First floor of the Backstage condo’s tower section.

Saturday, May 31

  • Clean-up and minor construction activities on site on site from 9:00 am to 1 pm

Monday, June 2

  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Tuesday, June 3

  • Rebar (steel) delivery starting at 7:00 am
  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Wednesday, June 4

  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Thursday, June 5 – Friday June 6

  • Moving the mobile crane.

  • PLEASE NOTE: The Esplanade will be closed to vehicular traffic from Yonge Street to the west TPA Lot entrance on the south and Scott Street on the north, while the crane work is conducted. Paid-Duty police officers will be on-site during the work. 

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


L Tower Construction Schedule May 31 – June 6

This is the current construction schedule for 8 The Esplanade – L Tower – May 31 – June 6, 2014

 

L Tower Yonge Street facade

L Tower Yonge Street facade

Saturday, May 31

  • There will be some general construction work inside the L Tower.

Monday, June 2

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, June 3

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, June 4

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, June 5

  • There will be general construction work inside the L Tower.

Friday, June 6

  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage Construction Schedule – May 24 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 24 – 30, 2014.

Backstage podium under construction

Backstage podium under construction

Please click here for general information on concrete pours.

 

Saturday, May 24

  • Excavation work on site from 9:00 am to Noon 
  • Some general interior work

Monday, May 26

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

 Tuesday, May 27

  • Fifth floor slab concrete pour #8 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Wednesday, May 28

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Thursday, May 29

  • Rebar (steel) delivery starting at 7:00 am.
  • Fifth floor slab concrete pour #9 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Friday, May 30

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


L Tower Construction Schedule May 24 – 30

This is the current construction schedule for 8 The Esplanade – L Tower – May 24 – 30, 2014

Looking north along the L Tower construction site on Yonge Street.

Looking north along the L Tower construction site on Yonge Street.

Saturday, May 24

  • There will be some general construction work inside the L Tower.

Monday, May 26 

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, May 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, May 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, May 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, May 30

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage Construction Schedule – May 17 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 17 – 23, 2014.

Backstage Condo - podium concrete detail.

Backstage Condo – podium concrete detail.

Please click here for general information on concrete pours.

 

Saturday, May 17

 

  • Excavation work on site from 9:00 am to Noon 
  • Some general interior work

Monday, May 19 – Victoria Day Holiday

  • Site Closed for the holiday.

 Tuesday, May 20

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Wednesday, May 21

  • Fifth floor slab concrete pour #7 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Thursday, May 22

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Friday, May 23

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


L Tower Construction Schedule May 17 – 23

This is the current construction schedule for 8 The Esplanade – L Tower –  May 17 – 23, 2014

L Tower as seen from King Street East and Scott Street

L Tower as seen from King Street East and Scott Street

Saturday, May 17

  • There will be some general construction work inside the L Tower.

Monday, May 19 – Victoria Day

  • Site closed for the holiday.

Tuesday, May 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, May 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, May 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, May 23

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

L Tower Construction Schedule May 10 – 16

L Tower from Front Street West

L Tower from Front Street West

This is the current construction schedule for 8 The Esplanade – L Tower –  May 10 – 16, 2014

Saturday, May 10

  • There will be some general construction work inside the L Tower.

Monday, May 12

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, May 13

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, May 14

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, May 15

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, May 16

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage Construction Schedule – May 12 – 16

Backstage at the Yonge Street Railway Bridge

Backstage at the Yonge Street Railway Bridge

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 12 – 16, 2014.

Please click here for general information on concrete pours.

Monday, May 12

  • Fifth floor slab concrete pour #4 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

 Tuesday, May 13

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Wednesday, May 14

  • Fifth floor slab concrete pour #5 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Thursday, May 15

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Friday, May 16

  • Fifth floor slab concrete pour #6 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Update – May 8 – 9

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for May 8 – 9, 2014.

 

Concrete Pump at Backstage Condominium

Concrete Pump at Backstage Condominium

Please click here for general information on concrete pours.

Thursday, May 8 – UPDATE

  • Fifth floor slab concrete pour #3 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Friday, May 9

  • Rebar (steel) delivery starting at 7:00 am.
  • Possible Wall & Column concrete pour from 1:00 pm to 6:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

 

L Tower Construction Schedule May 3 – 9

L Tower as seen from Union Station

L Tower as seen from Union Station

This is the current construction schedule for 8 The Esplanade – L Tower –  May 3 – 9, 2014

Saturday, May 3

  • There will be general construction work inside the L Tower.

Monday, May 5

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, May 6

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, May 7

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, May 8

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, May 9

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
%d bloggers like this: