Backstage Construction Schedule – April 12 – 18
April 11, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 12 – 18, 2014.
Please click here for general information on concrete pours.
Saturday, April 12
- Fifth floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 9:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 12:00 am – midnight.
- Please note this is long and complicated concrete pour. The scheduled start time is consistent with the City of Toronto Construction Noise By-Law as is the late completion, as concrete pours are exempted from the construction noise by-law. Why? Because once underway, they cannot be interrupted without compromising the structural integrity of the construction. The construction management team apologizes for any inconvenience this necessary work may cause.
Monday, April 14
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.
Tuesday, April 15
- Rebar (steel) delivery starting at 7:00 am.
Wednesday, April 16
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.
Thursday, April 17
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm..
Friday, April 18 – GOOD FRIDAY
Site Closed for the Holiday.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary Apr-12-18-2014