Backstage Construction Schedule – April 5 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 7 – 11, 2014.

Please click here for general information on concrete pours.

 Saturday, April 5

  • No work scheduled.

Monday, April 7

  • Putting a generator and related electrical equipment in place for the mobile crane. Work ongoing from 7:00 am.
  • There will be temporary lane closures, approximately 1 to 2 hours, on the eastbound traffic lane, Yonge to the west Toronto Parking Authority Driveway. 

 Tuesday, April 8

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

Wednesday, April 9

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

ThursdayApril 10

  • Fourth floor slab concrete pour #9, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Friday, April 11

  • Fourth floor slab concrete pour #10, by subcontractor Italform, scheduled to begin at 9:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: