Backstage Construction Schedule – April 5 – 11
April 4, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for April 7 – 11, 2014.
Please click here for general information on concrete pours.
Saturday, April 5
- No work scheduled.
Monday, April 7
- Putting a generator and related electrical equipment in place for the mobile crane. Work ongoing from 7:00 am.
- There will be temporary lane closures, approximately 1 to 2 hours, on the eastbound traffic lane, Yonge to the west Toronto Parking Authority Driveway.
Tuesday, April 8
- Rebar (steel) delivery starting at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.
Wednesday, April 9
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.
Thursday, April 10
- Fourth floor slab concrete pour #9, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Friday, April 11
- Fourth floor slab concrete pour #10, by subcontractor Italform, scheduled to begin at 9:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary Apr-5-11-2014