Backstage Construction UPDATE – March 26 – 28
March 26, 2014 Leave a comment
This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium – for March 26 – 28, 2014.
Please click here for general information on concrete pours.
Wednesday, March 26
- ADDED
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to run between 12:30 pm and 7:00 pm.
- CANCELLED
- Fourth floor slab concrete pour #7, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Thursday, March 27
- Rebar (steel) delivery starting at 7:00 am.
- Fourth floor slab concrete pour #7 part 1, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:30 pm.
Friday, March 28
- Fourth floor slab concrete pour #7 part 2, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 11:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.