Backstage Construction UPDATE – March 26 – 28

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  March 26 – 28, 2014.

Crane at Backstage Condominium

Crane at Backstage Condominium

Please click here for general information on concrete pours.

 

Wednesday, March 26

  • ADDED
    • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to run between 12:30 pm and 7:00 pm.
  • CANCELLED
    • Fourth floor slab concrete pour #7, by subcontractor Italform, scheduled to begin at 10:00 am.
    • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
    • Concrete Finishing to 10:00 pm.

Thursday, March 27

  • Rebar (steel) delivery starting at 7:00 am.
  • Fourth floor slab concrete pour #7 part 1, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:30 pm.

Friday, March 28

  • Fourth floor slab concrete pour #7 part 2, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 11:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: