Backstage Construction Schedule – March 17 – 21
March 17, 2014 Leave a comment
UPDATED March 14 – This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 17 – 21, 2014.
Please click here for general information on concrete pours.
Monday, March 17
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Tuesday, March 18
- Rebar (steel) delivery starting at 7:00 am.
- Crash Wall concrete pour, scheduled to begin at 10:00 am.
Wednesday, March 19
- Fourth floor slab concrete pour #5, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Thursday, March 20
- Crash Wall concrete pour, scheduled to begin at 9:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin once the Crash Wall pour is completed and should be finished by or before 7:00 pm.
Friday, March 21
- Rebar (steel) delivery starting at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30pm and should be finished by or before 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.