Backstage Construction Schedule – March 10 – 14, 2014

UPDATED March 14 – This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 10 – 14, 2014.

Please click here for general information on concrete pours.

First floor Backstage Condo, 1 The Esplanade

First floor Backstage Condo, 1 The Esplanade

 MondayMarch 10

  • Fourth floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

 Tuesday, March 11

  • Rebar (steel) delivery starting at 7:00 am.
  • Crash Wall concrete pour, scheduled to begin at 9:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin once the Crash Wall pour is completed and should be finished by or before 7:00 pm.

Wednesday, March 12

  • Elevator parts delivery starting at 7:00 am.
  • CANCELLED  – 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Thursday, March 13

  • CANCELLED
    • Fourth floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
    • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
    • Concrete Finishing to 10:00 pm.

Friday, March 14

  • Rebar (steel) delivery starting at 7:00 am.

CONCRETE POUR CANCELLED & RESCHEDULED TO SATURDAY MARCH 15 – 9:00 AM.

  • Fourth floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.
  • RESCHEDULED – Crash Wall concrete pour, scheduled to begin at 9:00 am.
  • RESCHEDULED – 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin once the Crash Wall pour is completed and should be finished by or before 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: