Backstage Construction Schedule – March 3 – 7, 2014
March 7, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for March 3 – 7, 2014.
Updated March 7/14
Please click here for general information on concrete pours.
Monday, March 3
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Tuesday, March 4
- Rebar (steel) delivery starting at 7:00 am.
- Fourth floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Wednesday, March 5
- ADDED:
- Link Line the contractor for Enbridge will be on site to install natural gas service to the Backstage condo. There will be a substantial impacts to eastbound vehicular traffic on The Esplanade between Younge and Scott Street for most of the day.
- Pedestrian traffic should be unaffected.
- The construction management team apologizes for any inconvenience this may cause.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Thursday, March 6
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Friday, March 7
- Rebar (steel) delivery starting at 7:00 am.
- ADDED:
- Fourth floor slab concrete pour #2 part 2, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
- CANCELLED: 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.
Please click on the link to the right to download a PDF copy of this week’s construction summary: Backstage & L Tower Construction Summary Mar-3-8-2014
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.