Backstage Construction Schedule – March 3 – 7, 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 3 – 7, 2014.

Updated March 7/14

Please click here for general information on concrete pours.

Podium poured into place at the Backstage Condominium

Podium poured into place at the Backstage Condominium

 MondayMarch 3

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

 Tuesday, March 4

  • Rebar (steel) delivery starting at 7:00 am.
  • Fourth floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Wednesday, March 5

  • ADDED:
    • Link Line the contractor for Enbridge will be on site to install natural gas service to the Backstage condo. There will be a substantial impacts to eastbound vehicular traffic on The Esplanade between Younge and Scott Street for most of the day.
    • Pedestrian traffic should be unaffected.
    • The construction management team apologizes for any inconvenience this may cause.

     

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Thursday, March 6

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, March 7

  • Rebar (steel) delivery starting at 7:00 am.
  • ADDED:
    • Fourth floor slab concrete pour #2 part 2, by subcontractor Italform, scheduled to begin at 10:00 am.
    • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
    • Concrete Finishing to 10:00 pm.
  • CANCELLED:  50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

Please click on the link to the right to download a PDF copy of this week’s construction summary: Backstage & L Tower Construction Summary Mar-3-8-2014

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: