Backstage & L Tower Construction Schedule for March 1

This is the construction schedule for 1 The Esplanade – Backstage condominium & 8 The Esplanade – L Tower  for  March 1, 2014.

Please click here for general information on concrete pours.

Backstage 

Saturday, March 1

  • Fourth floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 9:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:30 pm.

 L Tower

Saturday, March 1

  •  Weather Permitting the Hoist will be raised and Window Work will be undertaken. 

Please Note: Any work involving construction noise will be scheduled to begin at or after 9:00 am.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: