Backstage Construction Schedule – Feb 24 – 28, 2014 – updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 24 – 28, 2014.

UPDATED February 27

Please click here for general information on concrete pours.20140204_160056 (1)

 MondayFebruary 24

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

 Tuesday, February 25

  • Rebar (steel) delivery at 11:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

Wednesday, February 26

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

Thursday, February 27

  • CANCELLED DUE TO SEVER WEATHER:
    • Third floor slab concrete pour #11, by subcontractor Italform, scheduled to begin at 10:00 am.
    • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
    • Concrete Finishing to 10:00 pm.

Friday, February 28

  • Added: Rebar (steel) delivery starting at 7:00 am.
  • CANCELLED DUE TO SEVER WEATHER: 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

 

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: