L Tower Construction Schedule Feb 24 – 28, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  February 24 – 28 201420140214_131911

Please Note: there was unscheduled but necessary work conducted on Saturday, February 22 at the L Tower. A small motorized vehicle (a bobcat) was in operation from 7:30 am however the noise from its operation was well within City of Toronto guidelines. At 9:00 am a jackhammer was in use. We apologize for the lack of advance notice. 

Monday, February 24

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, February 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, February 26

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, February 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, February 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: