Backstage Construction Schedule – Feb 10 – 14, 2014
February 10, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for February 10 – 14, 2014.
Please click here for general information on concrete pours.
Monday, February 10
- Rebar (steel) delivery at 7:00 am.
- Third floor slab concrete pour #9 – part 1, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Tuesday, February 11
- Third floor slab concrete pour #9 – part 2, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Wednesday, February 12
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Thursday, February 13
- Rebar (steel) delivery at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Friday, February 14
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Feb-10-14