Backstage Construction Update for Feb 8, 2014

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  February 8, 2014.

Please click here for general information on concrete pours.

Saturday, February 8

Rescheduled from Friday, February 7 **

  • Third floor slab concrete pour #4 , by subcontractor Italform, scheduled to begin at 8:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 8:00 pm.

NOTES:

** Please note today’s (Friday, February 7) scheduled Slab Concrete Pour was cancelled as the concrete supplier was unable to deliver this morning. It might have been possible to have begun the pour this afternoon but that would have required concrete finishing until very late into the night. Instead today’s Slab Concrete Pour has been rescheduled to Saturday, February 8 as per the above notice.

  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

20140204_160056

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: