Backstage Construction Schedule – Feb 3 – 7, 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 3 – 7, 2014.

20140127_134044

Backstage Crane, illustrated view from Queen’s Quay & Lower Sherbourne

Please click here for general information on concrete pours.

UPDATED Feb 6/14

Monday, February 3

  • Rebar (steel) delivery at 7:00 am.
  • Third floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Tuesday, February 4

  • Rebar (steel) delivery at 7:00 am.
  • Second floor slab concrete pour #9, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Wednesday, February 5 – Snowstorm

  • CANCELLED – Rebar (steel) delivery at 7:00 am.
  • CANCELLED – Third floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
  • CANCELLED – After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • CANCELLED – Concrete Finishing to 10:00 pm.

Thursday, February 6

  • CANCELLED – Rebar (steel) delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, February 7

  • CANCELLED – 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Rescheduled from Wednesday

  • Third floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:30 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Feb-3-7

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: