Backstage & L Tower Construction Schedule for March 1

This is the construction schedule for 1 The Esplanade – Backstage condominium & 8 The Esplanade – L Tower  for  March 1, 2014.

Please click here for general information on concrete pours.

Backstage 

Saturday, March 1

  • Fourth floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 9:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:30 pm.

 L Tower

Saturday, March 1

  •  Weather Permitting the Hoist will be raised and Window Work will be undertaken. 

Please Note: Any work involving construction noise will be scheduled to begin at or after 9:00 am.

Backstage Construction Schedule – Feb 24 – 28, 2014 – updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 24 – 28, 2014.

UPDATED February 27

Please click here for general information on concrete pours.20140204_160056 (1)

 MondayFebruary 24

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

 Tuesday, February 25

  • Rebar (steel) delivery at 11:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

Wednesday, February 26

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

Thursday, February 27

  • CANCELLED DUE TO SEVER WEATHER:
    • Third floor slab concrete pour #11, by subcontractor Italform, scheduled to begin at 10:00 am.
    • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
    • Concrete Finishing to 10:00 pm.

Friday, February 28

  • Added: Rebar (steel) delivery starting at 7:00 am.
  • CANCELLED DUE TO SEVER WEATHER: 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 1:00 pm and should be completed before 7:00 pm.

 

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


L Tower Construction Schedule Feb 24 – 28, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  February 24 – 28 201420140214_131911

Please Note: there was unscheduled but necessary work conducted on Saturday, February 22 at the L Tower. A small motorized vehicle (a bobcat) was in operation from 7:30 am however the noise from its operation was well within City of Toronto guidelines. At 9:00 am a jackhammer was in use. We apologize for the lack of advance notice. 

Monday, February 24

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, February 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, February 26

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, February 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, February 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.


Backstage Construction Schedule – Feb 18 – 21, 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 10 – 14, 2014.

Please click here for general information on concrete pours.20140204_160150

 Tuesday, February 18

  • Rebar (steel) delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Wednesday, February 19

  • Third floor slab concrete pour #10, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Thursday, February 20

  • Rebar (steel) delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, February 21

  • Third floor slab concrete pour #11, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Feb-18-21

L Tower Construction Schedule Feb 18 – 21, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  February 18 – 21, 201420140204_155652

Tuesday, February 11

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, February 19

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, February 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, February 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Feb-18-21

Backstage Construction Update for Feb 14, 2014

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  February 14, 2014.

Please click here for general information on concrete pours.

Revised – Friday, February 8

Wall and column concrete pour cancelled and a slab pour added: 

  • Third floor slab concrete pour #6 – part 2, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:30 pm.

 

Backstage Construction Schedule – Feb 10 – 14, 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 10 – 14, 2014.20140204_160116

Please click here for general information on concrete pours.

Monday, February 10

  • Rebar (steel) delivery at 7:00 am.
  • Third floor slab concrete pour #9 – part 1, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Tuesday, February 11

  • Third floor slab concrete pour #9 – part 2, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Wednesday, February 12

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Thursday, February 13

  • Rebar (steel) delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, February 14

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Feb-10-14

L Tower Construction Schedule Feb 10 – 14, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  February 10 – 14, 201420140204_155652

Monday, February 10

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, February 11

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, February 12

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, February 13

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, February 14

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Feb-10-14

Backstage Construction Update for Feb 8, 2014

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  February 8, 2014.

Please click here for general information on concrete pours.

Saturday, February 8

Rescheduled from Friday, February 7 **

  • Third floor slab concrete pour #4 , by subcontractor Italform, scheduled to begin at 8:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 8:00 pm.

NOTES:

** Please note today’s (Friday, February 7) scheduled Slab Concrete Pour was cancelled as the concrete supplier was unable to deliver this morning. It might have been possible to have begun the pour this afternoon but that would have required concrete finishing until very late into the night. Instead today’s Slab Concrete Pour has been rescheduled to Saturday, February 8 as per the above notice.

  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

20140204_160056

Backstage Construction Update for Feb 7, 2014

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  February 7, 2014.

Please click here for general information on concrete pours.

UPDATED February 7

Friday, February 7

  • CANCELLED – 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Rescheduled to Saturday, February 8

  • CANCELLED – Third floor slab concrete pour #4 , by subcontractor Italform, scheduled to begin at 10:00 am.
  • CANCELLED – After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • CANCELLED – Concrete Finishing to 10:30 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


%d bloggers like this: