This a current construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  January 31, 2014.

Please click here for general information on concrete pours.

POSTED January 31 

Friday, January 31 – updated

  • Wall and Column Concrete Pour CANCELLED 
  • NEW: Third floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 