This a current construction update for 1 The Esplanade – L Tower parking and Backstage condominium – for January 31, 2014.
Please click here for general information on concrete pours.
POSTED January 31
Friday, January 31 – updated
- Wall and Column Concrete Pour CANCELLED
- NEW: Third floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.