Backstage Construction Schedule – January 27 – 31
January 27, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for January 27 – 31, 2014.
Please click here for general information on concrete pours.
POSTED January 26
Monday, January 27
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Tuesday, January 28
- Rebar (steel) delivery at 7:00 am.
- Second floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Wednesday, January 29
- Rebar (steel) delivery at 7:00 am and 10:00 am.
- Third floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:30 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:30 pm.
Thursday, January 30
- Rebar (steel) delivery at 7:00 am.
- Third floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Friday, January 31
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Jan-27-31