Backstage Construction Schedule – January 18 – 24 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 18 – 24, 2014.

Please click here for general information on concrete pours.Backstage-Condos-Street-Level-View

POSTED January 17

Saturday, January 18

  • Minor construction activities from 8:00 am to 1:00 pm.  

Monday, January 20

  • Rebar (steel) delivery at 7:00 am.
  • Third floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Tuesday, January 21

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Wednesday, January 22

  • Third floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Thursday, January 23

  • Rebar (steel) delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, January 24

  • Third floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Jan-18-24-2014

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: