Backstage Construction Schedule – January 11 – 17 2014 – UPDATED

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 11 – 14, 2014.

Please click here for general information on concrete pours.

POSTED January 10 – UPDATED January 14, 2014

Saturday, January 11

  • No exterior work. Rain Day.  

Monday, January 13

  • Rebar (steel) delivery at 7:00 am and 10:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Tuesday, January 14

  • Rebar (steel) delivery at 7:00 am.
  • CANCELLED – Third Floor slab concrete pour #1. 

Wednesday, January 15

  • Second floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Thursday, January 16

  • Rebar (steel) delivery at 7:00 am.
  • Third floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Friday, January 17

  • CANCELLED – Rebar Delivery
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Jan-11-17-2014-updated

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: