Backstage Construction Schedule – January 4 – 10 2014
January 4, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for January 4 – 10, 2014.
Please click here for general information on concrete pours.
UPDATED January 7, 2014
Saturday, January 4
- The air compressor will be used on the south side of the site. There will be construction noise from 9:00 am to 2:00 pm.
Monday, January 6
- Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 9:00 am.
- Rebar (steel) delivery to begin at 9:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
- Concrete finishing, scheduled to proceed until 9:00 PM.
Tuesday, January 7
- Cancelled: rebar delivery for use in the crash wall on the south side of the site–rescheduled to Monday, January 13.
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Wednesday, January 8
- CANCELLED: Third floor slab concrete pour #, by subcontractor Italform.
- CANCELLED: After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Thursday, January 9
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Friday, January 10
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Jan-4-10-14