Backstage Construction Schedule – January 4 – 10 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 4 – 10, 2014.

Please click here for general information on concrete pours.

UPDATED January 7, 2014

Saturday, January 4

  • The air compressor will be used on the south side of the site. There will be construction noise from 9:00 am to 2:00 pm. 

Monday, January 6

  • Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 9:00 am.
  • Rebar (steel) delivery to begin at 9:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
  • Concrete finishing, scheduled to proceed until 9:00 PM.

Tuesday, January 7

  • Cancelled: rebar delivery for use in the crash wall on the south side of the site–rescheduled to Monday, January 13. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Wednesday, January 8

  • CANCELLED: Third floor slab concrete pour #, by subcontractor Italform.
  • CANCELLED: After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Thursday, January 9

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, January 10

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Jan-4-10-14

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: