This a current construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  January 31, 2014.

Please click here for general information on concrete pours.

POSTED January 31 

Friday, January 31 – updated

  • Wall and Column Concrete Pour CANCELLED 
  • NEW: Third floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Backstage Construction Schedule – January 27 – 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 27 – 31, 2014.

Please click here for general information on concrete pours.the esplanade

POSTED January 26  

Monday, January 27

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Tuesday, January 28

  • Rebar (steel) delivery at 7:00 am.
  • Second floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Wednesday, January 29

  • Rebar (steel) delivery at 7:00 am and 10:00 am.
  • Third floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:30 pm.

Thursday, January 30

  • Rebar (steel) delivery at 7:00 am.
  • Third floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Friday, January 31

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Jan-27-31

L Tower Construction Schedule January 27 – 31, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  January 27 – 31, 2014

6a0133ee26fc70970b01a3fca56aaa970b-550wi

Image courtesy of Urban Toronto user Udo http://urbantoronto.ca/forum/member.php/1181-udo

Monday, January 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, January 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, January 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, January 30

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, January 31

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Jan-27-31

Backstage Construction Schedule – January 18 – 24 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 18 – 24, 2014.

Please click here for general information on concrete pours.Backstage-Condos-Street-Level-View

POSTED January 17

Saturday, January 18

  • Minor construction activities from 8:00 am to 1:00 pm.  

Monday, January 20

  • Rebar (steel) delivery at 7:00 am.
  • Third floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Tuesday, January 21

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Wednesday, January 22

  • Third floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Thursday, January 23

  • Rebar (steel) delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, January 24

  • Third floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Jan-18-24-2014

L Tower Construction Schedule January 20 -24, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  January 20 – 24, 2014

POSTED JANUARY 17L Tower

Monday, January 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, January 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, January 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, January 23

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, January 24

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Jan-18-24-2014

Late Concrete Finishing Tonight at Backstage

CONSTRUCTION UPDATE for Backstage January 15, 2014

Due to tower crane mechanical problems the duration of today’s slab pour went late. Concrete finishing will extend to 12:30 am. 

The construction management team apologizes for any inconvenience this may cause. 

Backstage Construction Schedule – January 11 – 17 2014 – UPDATED

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 11 – 14, 2014.

Please click here for general information on concrete pours.

POSTED January 10 – UPDATED January 14, 2014

Saturday, January 11

  • No exterior work. Rain Day.  

Monday, January 13

  • Rebar (steel) delivery at 7:00 am and 10:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Tuesday, January 14

  • Rebar (steel) delivery at 7:00 am.
  • CANCELLED – Third Floor slab concrete pour #1. 

Wednesday, January 15

  • Second floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Thursday, January 16

  • Rebar (steel) delivery at 7:00 am.
  • Third floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:00 pm.

Friday, January 17

  • CANCELLED – Rebar Delivery
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Jan-11-17-2014-updated

L Tower Construction Schedule January 13 – 17, 2014 – UPDATED

This is the current construction schedule for 8 The Esplanade – L Tower –  January 13 – 17, 2014

POSTED JANUARY 10 – Updated January 14

6a0133ee26fc70970b017744ae8110970d-550wiMonday, January 13

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, January 14

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, January 15

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, January 16

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, January 17

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Jan-11-17-2014-updated

Backstage Construction Schedule – January 4 – 10 2014

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 4 – 10, 2014.

Please click here for general information on concrete pours.

UPDATED January 7, 2014

Saturday, January 4

  • The air compressor will be used on the south side of the site. There will be construction noise from 9:00 am to 2:00 pm. 

Monday, January 6

  • Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 9:00 am.
  • Rebar (steel) delivery to begin at 9:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
  • Concrete finishing, scheduled to proceed until 9:00 PM.

Tuesday, January 7

  • Cancelled: rebar delivery for use in the crash wall on the south side of the site–rescheduled to Monday, January 13. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Wednesday, January 8

  • CANCELLED: Third floor slab concrete pour #, by subcontractor Italform.
  • CANCELLED: After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Thursday, January 9

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Friday, January 10

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Jan-4-10-14

L Tower Construction Schedule January 6 – 10, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  January 6 – 10, 2014

POSTED JANUARY 3

Monday, January 6

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, January 7

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, January 8

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, January 9

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, January 10

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Jan-4-10-14

%d bloggers like this: