January 14, 2014
by EN Consulting Group
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for January 11 – 14, 2014.
Please click here for general information on concrete pours.
POSTED January 10 – UPDATED January 14, 2014
Saturday, January 11
- No exterior work. Rain Day.
Monday, January 13
- Rebar (steel) delivery at 7:00 am and 10:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
Tuesday, January 14
- Rebar (steel) delivery at 7:00 am.
- CANCELLED – Third Floor slab concrete pour #1.
Wednesday, January 15
- Second floor slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Thursday, January 16
- Rebar (steel) delivery at 7:00 am.
- Third floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
- Concrete Finishing to 10:00 pm.
Friday, January 17
- CANCELLED – Rebar Delivery
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.