Backstage Construction Schedule – December 23 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for   December 23 – 27, 2013

Please click here for general information on concrete pours.

Posted December 20

Monday, December 23

  • Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 9:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed. 
  • Concrete finishing, scheduled to proceed until 9:00 PM.

Tuesday, December 17

  • There will be some minimal construction activity on site during the day.

HAPPY HOLIDAYSchristmas-tree-pics-0111

Christmas Day

  • Site closed for the holiday. 

Boxing Day

  • Site closed for the holiday.

Friday, December 27

  • Site closed.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Tuesday this week, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Dec-23-27-2013


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: