Backstage Construction Schedule – December 7 – 13
December 6, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 7 – 13, 2013
Please click here for general information on concrete pours.
Posted December 6
Saturday, December 7
- Labourers will be on-site chipping concrete . The work is scheduled to begin at 9:00 am and should be completed by midday.
Monday, December 9
- There will be a rebar delivery at 10:00 am.
- Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin after 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
- Concrete finishing, scheduled to proceed until 8:00 PM.
Tuesday, December 10
- There will be a rebar delivery at 7:00 am.
- Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
- Concrete finishing, scheduled to proceed until 8:00 PM.
Wednesday, December 11
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:00 pm and should be completed before 7:00 pm.
Thursday, December 12
- Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
- Concrete finishing, scheduled to proceed until 8:00 PM.
Friday, December 13
- There will be a rebar delivery at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. The pour is scheduled to begin at 12:00 pm and should be completed before 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Dec 7-13-2013