Backstage Construction Update – November 25
November 25, 2013 Leave a comment
This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium – for November 25, 2013.
Please click here for general information on concrete pours.
Posted November 25
Monday, November 25
- Today’s second floor slab pour has been delayed due to complications with the pour.
- Concrete finishing, is now scheduled to proceed until 11:30 pm. The construction management team apologizes for any inconvenience this may cause.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 25-29–2013