Backstage Construction Schedule – November 25 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  November 25 – 29, 2013

Construction progress at Backstage On The Esplanade, image by Jack Landau http://urbantoronto.ca

Construction progress at Backstage On The Esplanade, image by Jack Landau http://urbantoronto.ca

Please click here for general information on concrete pours.

Posted November 22

Monday, November 25

  • Pouring second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed. 
  • Concrete finishing, scheduled to proceed until 10:00 PM.

Tuesday, November 26

  • There will be a rebar delivery at 7:00 am. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, November 27

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, November 28

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, November 29

  • There will be a rebar delivery at 7:00 am. 
  • Pouring second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
  • Concrete finishing, scheduled to proceed until 10:00 PM.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 25-29–2013


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: