Backstage Construction Schedule – November 16 – 22

admin-ajax.php

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  November 16 – 22, 2013

Please click here for general information on concrete pours.

Posted November 15

Saturday, November 16

  • Chipping concrete along the south wall using an air compressor and breaker. This work is scheduled to occur between 9:00 am and 2:00 pm.

Monday, November 18

  • Pouring second floor slab pour #5 – part 2, by subcontractor Italform. The pour is scheduled to begin at 10:30 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:30 PM.

Tuesday, November 19

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, November 20

  • There will be a rebar delivery at 7:00 am. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, November 21

  • Pouring second floor slab pour #5 – part 3, by subcontractor Italform. The pour is scheduled to begin at 10:30 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:30 PM.

Friday, November 22

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 16-18–2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: