Backstage Construction Schedule – November 2 – 8
November 1, 2013 Leave a comment

Aerial view of the Backstage Condo construction site courtesy of Cityzen Real Estate Group. http://cityzen.typepad.com/
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 2 – 8, 2013
Please click here for general information on concrete pours.
Posted November 1
Saturday, November 2
- Using the air compressor to break concrete on the south wall of the site. This work is scheduled to begin at 9:00 pm and should be completed no later than 3:00 pm.
Monday, November 4
- Pouring second floor slab pour #1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 10:30 PM.
Tuesday, November 5
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Wednesday, November 6
- Pouring second floor slab pour #4, by subcontractor Italform. The pour is scheduled to begin at 11:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 10:30 PM.
Thursday, November 7
- There will be a rebar delivery at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Friday, November 8
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 2-8–2013