Backstage Construction Schedule – November 30 – December 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  November 23 – December 6, 201320131128_101115

Please click here for general information on concrete pours.

Posted November 29

Saturday, November 30

  • Breaking concrete on the south wall using an air compressor and breakers. The work is scheduled to begin at 9:00 am and should be completed by 4:00 pm.

Monday, December 2

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, December 3

  • Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed. 
  • Concrete finishing, scheduled to proceed until 10:00 PM.

Wednesday, December 4

  • There will be a rebar delivery at 7:00 am. 
  • Second floor ramp slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed. 
  • Concrete finishing, scheduled to proceed until 10:00 PM.

Thursday, December 5

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, December 6

  • There will be a rebar delivery at 7:00 am. 
  • Second floor ramp slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed. 
  • Concrete finishing, scheduled to proceed until 10:00 PM.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 30- Dec 6-2013


L Tower Construction Schedule December 2 – 6

This is the current construction schedule for 8 The Esplanade – L Tower –  December 2 – 6, 201320131128_101011

Posted November 29

Monday, December 2

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, December 3

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, December 4

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, December 5

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, December 6

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 30- Dec 6-2013

Backstage Construction Update – November 25

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  November 25, 2013.

Please click here for general information on concrete pours.

Posted November 25

Monday, November 25

  • Today’s second floor slab pour has been delayed due to complications with the  pour.
  • Concrete finishing, is now scheduled to proceed until 11:30 pm. The construction management team apologizes for any inconvenience this may cause.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 25-29–2013


Backstage Construction Schedule – November 25 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  November 25 – 29, 2013

Construction progress at Backstage On The Esplanade, image by Jack Landau http://urbantoronto.ca

Construction progress at Backstage On The Esplanade, image by Jack Landau http://urbantoronto.ca

Please click here for general information on concrete pours.

Posted November 22

Monday, November 25

  • Pouring second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed. 
  • Concrete finishing, scheduled to proceed until 10:00 PM.

Tuesday, November 26

  • There will be a rebar delivery at 7:00 am. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, November 27

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, November 28

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, November 29

  • There will be a rebar delivery at 7:00 am. 
  • Pouring second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
  • Concrete finishing, scheduled to proceed until 10:00 PM.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 25-29–2013


L Tower Construction Schedule November 25 – 29

One of L Tower's 2-storey penthouses, image by Jack Landau from Urban Toronto - http://urbantoronto.ca

One of L Tower’s 2-storey penthouses, image by Jack Landau from Urban Toronto – http://urbantoronto.ca

This is the current construction schedule for 8 The Esplanade – L Tower –  November 25 – 29, 2013

Posted November 22

Monday, November 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, November 26

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, November 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, November 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 25-29–2013

Backstage Concrete Pour update for the evening of November 15

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  the evening of November 15, 2013

Please click here for general information on concrete pours.

Posted November 15

 Friday, November 15

  • Issues with concrete slab pour #4 have delayed the pouring process. Unfortunately this will extend the concrete finishing process until  11:30 PM. 
  • The Construction Management team apologizes for any inconvenience this may cause.

Backstage Construction Schedule – November 16 – 22

admin-ajax.php

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  November 16 – 22, 2013

Please click here for general information on concrete pours.

Posted November 15

Saturday, November 16

  • Chipping concrete along the south wall using an air compressor and breaker. This work is scheduled to occur between 9:00 am and 2:00 pm.

Monday, November 18

  • Pouring second floor slab pour #5 – part 2, by subcontractor Italform. The pour is scheduled to begin at 10:30 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:30 PM.

Tuesday, November 19

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, November 20

  • There will be a rebar delivery at 7:00 am. 
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, November 21

  • Pouring second floor slab pour #5 – part 3, by subcontractor Italform. The pour is scheduled to begin at 10:30 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:30 PM.

Friday, November 22

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 16-18–2013

L Tower Construction Schedule November 18 – 22

This is the current construction schedule for 8 The Esplanade – L Tower –  November 18 – 22, 2013

Posted November 15

Monday, November 18

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, November 19

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, November 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, November 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 16-18–2013

Backstage Construction Update for November 15

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  November 15, 2013

Please click here for general information on concrete pours.

Posted November 14

 Friday, November 15

  • Rebar delivery at 7:00 am.
  • Pouring second floor slab pour #4, by subcontractor Italform. The pour is scheduled to begin at 10:30 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete finishing, scheduled to proceed until 10:30 PM.

Backstage Construction Schedule – November 11 – 15

admin-ajax.php

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  November 11 – 15, 2013

Please click here for general information on concrete pours.

Posted November 8

 

Monday, November 11

  • Pouring second floor slab pour #5, by subcontractor Italform. The pour is scheduled to begin at 10:30 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:30 PM.

Tuesday, November 12

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, November 13

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, November 14

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, November 15

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 11-15–2013