Backstage Construction Schedule – November 30 – December 6
November 29, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 23 – December 6, 2013
Please click here for general information on concrete pours.
Posted November 29
Saturday, November 30
- Breaking concrete on the south wall using an air compressor and breakers. The work is scheduled to begin at 9:00 am and should be completed by 4:00 pm.
Monday, December 2
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Tuesday, December 3
- Second floor slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
- Concrete finishing, scheduled to proceed until 10:00 PM.
Wednesday, December 4
- There will be a rebar delivery at 7:00 am.
- Second floor ramp slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
- Concrete finishing, scheduled to proceed until 10:00 PM.
Thursday, December 5
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Friday, December 6
- There will be a rebar delivery at 7:00 am.
- Second floor ramp slab pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin after the slab pour is completed.
- Concrete finishing, scheduled to proceed until 10:00 PM.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Nov 30- Dec 6-2013