Backstage Construction Update – November 1
October 31, 2013 Leave a comment
This is the construction update for 1 The Esplanade – Backstage condominium – for November 1, 2013
Please click here for general information on concrete pours.
UPDTED October 31
Friday, November 1
- There will be a rebar delivery at 7:00 am.
- Pouring second floor slab pour by subcontractor Italform. The pour is tentatively scheduled to begin 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 10:00 PM.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.