Backstage Construction Update – November 1

This is the construction update for 1 The Esplanade – Backstage condominium for  November 1, 2013

Please click here for general information on concrete pours.

UPDTED October 31

Friday, November 1

  • There will be a rebar delivery at 7:00 am.
  • Pouring second floor slab pour by subcontractor Italform. The pour is tentatively  scheduled to begin 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:00 PM.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: