Backstage Construction Schedule – October 12 – 18

1375830_10151721165824779_427224887_n

Backstage Construction site – image courtesy of Cityzen Real Estate Group

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  October  12 – 18, 2013

Please click here for general information on concrete pours.

Posted October 11

ee
Saturday, October 12

  • Breaking concrete on the south wall of the site. This work is scheduled to begin at 9:00 pm and should be completed no later than 3:00 pm.

Monday, October 14 – THANKSGIVING HOLIDAY – site closed

Tuesday, October 15

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, October 16

  • There will be a rebar delivery at 11:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, October 17

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, October 18

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Oct 12-18-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: