Backstage Construction Update – November 1

This is the construction update for 1 The Esplanade – Backstage condominium for  November 1, 2013

Please click here for general information on concrete pours.

UPDTED October 31

Friday, November 1

  • There will be a rebar delivery at 7:00 am.
  • Pouring second floor slab pour by subcontractor Italform. The pour is tentatively  scheduled to begin 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:00 PM.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – October 26 – November 1

1267262_10151721165824779_427224887_o

Aerial view of the Backstage Condo construction site courtesy of Cityzen Real Estate Group. http://cityzen.typepad.com/

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  October  26  – November 1, 2013

Please click here for general information on concrete pours.

UPDTED October 31

Saturday, October 26

  • Using the hydraulic breaker and air compressor to break concrete on the south wall  of the site. This work is scheduled to begin at 9:00 pm and should be completed no later than 3:00 pm.

Monday, October 28

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, October 29 – UPDATED

  • Pouring second floor slab pour #3, part 1, by subcontractor Italform. The pour is scheduled to begin midday.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 11:30 PM.

Wednesday, October 30

  • Pouring second floor slab pour #3, part 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10 PM.

Thursday, October 31

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, November 1 – UPDATED

  • There will be a rebar delivery at 7:00 am.
  • Pouring second floor slab pour by subcontractor Italform. The pour is tentatively  scheduled to begin 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:00 PM.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Oct 26-Nov 1–2013

Backstage Concrete Pour UPDATE for October 29

Please note: that the tentatively scheduled 2nd floor concrete slab pour at the Backstage Condo site is underway today and unfortunately will require concrete finishing until 11:30 pm this evening.

The construction management team apologies for any inconvenience this may cause.

Please click here for the full updated Backstage construction schedule for the week of October 28. 

NOTE: Concrete pours are exempt from the City of Toronto Construction Noise By-law weekday hours of 7:00 am to 7:00 pm.

L Tower Construction Schedule October 28 – November 1

L Tower seen from Yonge and Front, image by Jack Landau, courtesy of http://urbantoronto.ca

L Tower seen from Yonge and Front, image by Jack Landau, courtesy of http://urbantoronto.ca

This is the current construction schedule for 8 The Esplanade – L Tower –  October 28 – November 1, 2013

Posted October 25

Monday, October 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, October 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, October 30

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, October 31

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 1

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Oct 26-Nov 1–2013

Backstage Construction Schedule – October 19 – 25

1375830_10151721165824779_427224887_n

Backstage Construction site – image courtesy of Cityzen Real Estate Group

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  October  19 – 25, 2013

Please click here for general information on concrete pours.

Posted October 19

ee

Saturday, October 19

  • Using the mini-excavator to break concrete on the northeast side  of the site. This work is scheduled to begin at 9:00 pm and should be completed no later than 4:00 pm.

Monday, October 21

  • There will be a rebar delivery at 10:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, October 22

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, October 23

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, October 24

  • Pouring second floor slab pour #1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10 PM.

Friday, October 25

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Oct 19-25-2013

L Tower Construction Schedule October 21 – 25

L Tower detail, Yonge and The Esplanade

This is the current construction schedule for 8 The Esplanade – L Tower –  October 21 – 25, 2013

Posted October 18

Monday, October 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, October 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, October 23

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, October 24

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, October 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Oct 19-25-2013

City of Toronto Storm Water Work Yonge & The Esplanade – October 11 – 13

Posted October 11

Please Note: 

    We have been advised that City of Toronto contractor OJCR will be working at Yonge Street and The Esplanade starting Friday night, October 11 through to Sunday, October 13, on storm water connections. We anticipate that there may be disruptions to traffic flow and possibly pedestrian access to The Esplanade from Yonge Street. 

Backstage Construction Schedule – October 12 – 18

1375830_10151721165824779_427224887_n

Backstage Construction site – image courtesy of Cityzen Real Estate Group

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  October  12 – 18, 2013

Please click here for general information on concrete pours.

Posted October 11

ee
Saturday, October 12

  • Breaking concrete on the south wall of the site. This work is scheduled to begin at 9:00 pm and should be completed no later than 3:00 pm.

Monday, October 14 – THANKSGIVING HOLIDAY – site closed

Tuesday, October 15

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, October 16

  • There will be a rebar delivery at 11:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, October 17

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, October 18

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Oct 12-18-2013

L Tower Construction Schedule October 15 – 18

1255470_10151663186404779_458404639_n

L Tower – image courtesy of Cityzen Real Estate Group

This is the current construction schedule for 8 The Esplanade – L Tower –  October 15 – 18, 2013

Posted October 11

Monday, October 14 – THANKSGIVING HOLIDAY – site closed

Tuesday, October 15

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, October 16

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, October 17

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, October 18

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Oct 12-18-2013

Backstage Construction Schedule – October 7 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  October  7 – 11, 2013

Please click here for general information on concrete pours.

Posted October 4

Monday, October 7

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, October 8

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, October 9

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, October 10

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, October 11

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Oct-7-11-2013