October 31, 2013
by EN Consulting Group
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for October 26 – November 1, 2013
Please click here for general information on concrete pours.
UPDTED October 31
Saturday, October 26
- Using the hydraulic breaker and air compressor to break concrete on the south wall of the site. This work is scheduled to begin at 9:00 pm and should be completed no later than 3:00 pm.
Monday, October 28
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Tuesday, October 29 – UPDATED
- Pouring second floor slab pour #3, part 1, by subcontractor Italform. The pour is scheduled to begin midday.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 11:30 PM.
Wednesday, October 30
- Pouring second floor slab pour #3, part 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 10 PM.
Thursday, October 31
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Friday, November 1 – UPDATED
- There will be a rebar delivery at 7:00 am.
- Pouring second floor slab pour by subcontractor Italform. The pour is tentatively scheduled to begin 10:00 am.
- After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 10:00 PM.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Oct 26-Nov 1–2013