Backstage Construction Schedule – September 28 – October 4
September 27, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 28 – October 4, 2013
Please click here for general information on concrete pours.
Updated October 1
Saturday, September 28
- Plumbing work on site at Parking Level 5.
Monday, September 30
- Elevator equipment delivery at 7:00 am.
- Pouring ground floor slab pour #7, part1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 10 PM.
Tuesday, October 1
- Elevator equipment delivery at 7:00 am.
- Pouring ground floor slab pour #7, part1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 10 PM.
Wednesday, October 2
- A small ground floor slab concrete pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
- After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
- Concrete finishing, scheduled to proceed until 8 PM.
Thursday, October 3
- Elevator equipment delivery at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Friday, October 4
- There will be a rebar delivery at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary SEP 28-Oct 4-2013