Backstage Construction Schedule – September 21 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  September 21 – September 27, 2013

Please click here for general information on concrete pours.

Posted September 20

Saturday, September 20

  • From 9:00 am to to approximately 4 :00 pm the compressor will be used to break up concrete in the tunnel.

Monday, September 23

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, September 24

  • Pouring ground floor slab, pour #6 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.

Wednesday, September 25

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, September 26

  • There will be a rebar delivery at 7:00 am.
  • Pouring ground floor slab pour #8 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.

Friday, September 27

  • There will be a rebar delivery at 10:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary SEP 21-27-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: