Backstage Construction Schedule – September 21 – 27
September 20, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for September 21 – September 27, 2013
Please click here for general information on concrete pours.
Posted September 20
Saturday, September 20
- From 9:00 am to to approximately 4 :00 pm the compressor will be used to break up concrete in the tunnel.
Monday, September 23
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Tuesday, September 24
- Pouring ground floor slab, pour #6 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
Wednesday, September 25
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Thursday, September 26
- There will be a rebar delivery at 7:00 am.
- Pouring ground floor slab pour #8 by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
Friday, September 27
- There will be a rebar delivery at 10:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary SEP 21-27-2013