Backstage Construction Schedule – August 31 – September 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 31 – September 6 , 2013

Please click here for general information on concrete pours.

Please note that the site will be closed on Monday, September 2 for Labour Day. Have a safe and happy holiday weekend. 

Posted August 30

Saturday, August 31

  • An hydraulic breaker will be operating at the west side of site, breaking concrete from 9:00 am through 4:00 pm

Monday, September 2 – Site Closed for the Labour Day holiday.

Tuesday, September 3

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, September 4 

  • There will be a rebar delivery at 9:00 am.
  • Concrete pour #2, part 1, for the Ground Floor slab, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.

Thursday, September 5

  • Concrete pour #2, part 2, for the Ground Floor slab, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.

Friday, September 6

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Aug-31-Sep-6-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: