Backstage Construction Schedule – August 24 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 24 – 30 , 2013

Please click here for general information on concrete pours.

Posted August 23

Saturday, August 24

  • A mini-excavator with a hydraulic breaker will be operating at the west side of site, breaking concrete from 9:00 am through 4:00 pm

Monday, August 26

  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, August 27

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, August 28

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, August 29

  • 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Friday, August 30

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary August 24-30-2013

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: