Backstage Construction Schedule – August 31 – September 6
August 30, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for August 31 – September 6 , 2013
Please click here for general information on concrete pours.
Please note that the site will be closed on Monday, September 2 for Labour Day. Have a safe and happy holiday weekend.
Posted August 30
Saturday, August 31
- An hydraulic breaker will be operating at the west side of site, breaking concrete from 9:00 am through 4:00 pm
Monday, September 2 – Site Closed for the Labour Day holiday.
Tuesday, September 3
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
Wednesday, September 4
- There will be a rebar delivery at 9:00 am.
- Concrete pour #2, part 1, for the Ground Floor slab, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
Thursday, September 5
- Concrete pour #2, part 2, for the Ground Floor slab, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
Friday, September 6
- There will be a rebar delivery at 7:00 am.
- 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Aug-31-Sep-6-2013