Backstage Construction Schedule – August 31 – September 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 31 – September 6 , 2013

Please click here for general information on concrete pours.

Please note that the site will be closed on Monday, September 2 for Labour Day. Have a safe and happy holiday weekend. 

Posted August 30

Saturday, August 31

  • An hydraulic breaker will be operating at the west side of site, breaking concrete from 9:00 am through 4:00 pm

Monday, September 2 – Site Closed for the Labour Day holiday.

Tuesday, September 3

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, September 4 

  • There will be a rebar delivery at 9:00 am.
  • Concrete pour #2, part 1, for the Ground Floor slab, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.

Thursday, September 5

  • Concrete pour #2, part 2, for the Ground Floor slab, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.

Friday, September 6

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary Aug-31-Sep-6-2013

L Tower Construction Schedule September 3 – 6

This is the current construction schedule for 8 The Esplanade – L Tower –  September 3 – 6, 2013

Posted August 30

Please note that the site will be closed on Monday, September 2 for Labour Day. Have a safe and happy holiday weekend. 

Tuesday, September 3

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, September 4

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, September 5

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, September 6

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Aug-31-Sep-6-2013 

UPDATED Backstage Construction Schedule – August 27 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 27 – 30 , 2013

Please click here for general information on concrete pours.

Updated August 26

Monday, August 26

  • Due to weather conditions no work was performed.

Tuesday, August 27

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, August 28

  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, August 29

  • 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Friday, August 30

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: UPDATED Backstage Construction Summary August 27-30-2013

Backstage Construction Schedule – August 24 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 24 – 30 , 2013

Please click here for general information on concrete pours.

Posted August 23

Saturday, August 24

  • A mini-excavator with a hydraulic breaker will be operating at the west side of site, breaking concrete from 9:00 am through 4:00 pm

Monday, August 26

  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, August 27

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, August 28

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, August 29

  • 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Friday, August 30

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary August 24-30-2013

L Tower Construction Schedule August 24 – August 30

This is the current construction schedule for 8 The Esplanade – L Tower –  August 24 – August 30, 2013

Posted August 23, 2013

Monday, August 26

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, August 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, August 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, August 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, August 30

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary August 24-30-2013

 

Tuesday Morning Deliveries, August 20

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 20, 2013

Updated August 20

Tuesday Morning Deliveries, August 20

On behalf of the site management team at Backstage, please accept our apologies if you were bothered by any significant truck noise earlier this morning, prior to 7:00 am. The subcontractors have been explicitly told not to arrive at the site prior to 7:00 am. Drivers who may arrive just before 7:00 am have been instructed to hold and wait till 7:00 am before making any delivery to the site. Many thanks for your understanding. If you have any questions or concerns please contact us at: ltowerconstructioninfo@enconsulting.ca.

 

Backstage Concrete Pour UPDATE – August 19

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 19, 2013

Please click here for general information on concrete pours.

Updated August 19.

Monday, August 19

  • Please be advised that due to unforeseen circumstances concrete finishing at Backstage will unfortunately go past 11:00 pm tonight. Every effort will be made to complete the work as soon as possible. 
     
    We apologize for any inconvenience this may cause and thank you in advance for your kind understanding. 

L Tower Construction Schedule August 19 – August 23

This is the current construction schedule for 8 The Esplanade – L Tower –  August 19 – August 23, 2013

Posted August 16, 2013

Monday, August 19

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, August 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, August 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, August 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, August 23

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary August 17-23-2013

 

Backstage Construction Schedule – August 17 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 17 – 23 , 2013

Please click here for general information on concrete pours.

Posted August 16

Saturday, August 17

  • A mini-excavator with a hydraulic breaker will be operating at the west side of site, breaking concrete from 9:00 am through 4:00 pm

Monday, August 19

  • Concrete pour #7 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.

Tuesday, August 20

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #5 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, August 21

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, August 22

  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Friday, August 23

  • Concrete pour #6 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary August 17-23-2013

Backstage Construction Schedule – August 10 – 16

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 10 – 16 , 2013

Please click here for general information on concrete pours.

Posted August 9

Saturday, August 10

  • A mini-excavator with a hydraulic breaker will be operating at the west side of site, breaking concrete from 9:00 am through 4:00 pm

Monday, August 12

  • Concrete pour #3 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, August 13

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, August 14

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Thursday, August 15

  • Concrete pour #4 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Friday, August 16

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary August 10-16-2013

%d bloggers like this: