Backstage Construction Schedule – July 29 – August 2
July 26, 2013 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for July 29 – August 2, 2013
Please click here for general information on concrete pours.
Posted July 26.
Monday, July 29
- Concrete pour #6 for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed by 10:0pm.
- After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.
Tuesday, July 30
- There will be a rebar delivery at 7:00 am.
- Concrete pour 6, part 2, for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed by 10:00 pm.
- After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.
Wednesday, July 31
- Concrete pour #1 for parking level 1 – cancelled due to weather conditions .
Thursday, August 1
- Concrete pour #1 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.
Friday, August 2
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.
Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 29-Aug-2-2013