Backstage Construction Update August 1 – 2
July 31, 2013 Leave a comment
This is the current construction UPDATE for 1 The Esplanade – L Tower parking and Backstage condominium – for August 1- 2, 2013
Please click here for general information on concrete pours.
Posted July 31, 2013
Please Note: Wednesday’s scheduled concrete pours were cancelled due to weather conditions and rescheduled to August 1.
Thursday, August 1
- Concrete pour #1 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
- After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.
Friday, August 2
- 50 cubic metre, wall and column concrete pour by subcontractor Italfor. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.