Backstage Construction Update August 1 – 2

This is the current construction UPDATE for 1 The Esplanade – L Tower parking and Backstage condominium for  August  1- 2, 2013

Please click here for general information on concrete pours.

Posted July 31, 2013

Please Note: Wednesday’s scheduled concrete pours were cancelled due to weather conditions and rescheduled to August 1. 

Thursday, August 1

  • Concrete pour #1 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Friday, August 2

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – July 29 – August 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  July 29 – August 2, 2013

Please click here for general information on concrete pours.

Posted July 26.

Monday, July 29

  • Concrete pour #6 for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed by 10:0pm.
  • After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Tuesday, July 30

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour 6, part 2, for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed by 10:00 pm.
  • After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Wednesday, July 31

  • Concrete pour #1 for parking level 1 – cancelled due to weather conditions .

Thursday, August 1

  • Concrete pour #1 for parking level 1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre, wall concrete pour by subcontractor Italform. The pour is scheduled to begin after the slab pour is completed and should be completed no later than 7:00 pm.

Friday, August 2

  • 50 cubic metre, wall and column concrete pour by subcontractor Italfor. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 29-Aug-2-2013

L Tower Construction Schedule July 29 – August 2

This is the current construction schedule for 8 The Esplanade – L Tower –  July 29 – August 2,  2013

Posted July 26, 2013

Monday July 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, July 30

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, July 31

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, August 1

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, August 2

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 29-Aug-2-2013

 

Backstage Construction Schedule – July 22 – 26

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  July 22 – 26, 2013

Please click here for general information on concrete pours.

Posted July 19.

Monday, July 22

  • Concrete pour #4 for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:0pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, July 23

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, July 24

  • Concrete pour #5 for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, July 25

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, July 26

  • There will be a rebar delivery at 7:00 am.
  • Concrete pour #7 for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Update – L Tower & Backstage Construction Summary July 22-26

L Tower Construction Schedule July 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower –  July 22 – 26,  2013

Posted July 19, 2013

Monday July 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, July 23

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, July 24

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, July 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, July 26

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Update – L Tower & Backstage Construction Summary July 22-26

 

Backstage Construction Schedule – July 15 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  July 15 – 19, 2013

Please click here for general information on concrete pours.

Posted July 12.

Monday, July 15

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, July 16

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, July 17

  • Slab concrete pour for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:30 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, July 18

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, July 19

  • There will be a rebar delivery at 7:00 am.
  • Slab concrete pour for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:30 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 15-19-2013

L Tower Construction Schedule July 15 -19

This is the current construction schedule for 8 The Esplanade – L Tower –  July 15 – 19,  2013

Posted July 12, 2013

Monday July 15

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, July 16

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, July 17

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, July 18

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, July 19

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 15-19-2013

 

The Esplanade reopens to vehicles btwn Yonge & Scott

Yesterday’s closure of the eastbound vehicle lane on The Esplanade between Yonge & Scott Street will end this afternoon with the reopening of the vehicle lane. Pedestrian access has been maintained throughout the day. 

The Backstage & L Tower Parking construction schedule for July 8 – 12 was unaffected by the storm and remains on track. Please click here to view it.

The Esplanade closed from Yonge to Scott

Please note that due to a water-main break earlier today on Front Street, east of Scott Street there are two temporary road closures:

  1. Front Street is closed from Scott Street to Church Street.
  2. Toronto Police Services and the City of Toronto Works Department have also asked for The Esplanade to be closed from Younge Street to Scott Street to minimize traffic in the area.

There is no information on the duration of this closure at this time. Once we have more information we will post it here.

Backstage Construction Schedule – July 8 – 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  July 8 – 12, 2013

Please click here for general information on concrete pours.

Posted July 5.

Monday, July 8

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Tuesday, July 9

  • There will be a rebar delivery at 7:00 am.
  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Wednesday, July 10

  • Concrete pour #2 for parking level 2, by subcontractor Italform. The pour is scheduled to begin at 10:00 am and concrete finishing should be completed no later than 10:00 pm.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Thursday, July 11

  • A 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at approximately 12:30 pm and should be completed no later than 7:00 pm.

Friday, July 12

  • There will be a rebar delivery at 7:00 am.
  • A  50 cubic metre wall and column concrete pour by subcontractor ItalformThis pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary July 8-12-2013